Prompt Payment Rules in Ontario Construction Contracts

Covers the proper invoice requirement, the cascading 28-day and 7-day payment timelines, notices of non-payment, and how the regime is meant to keep money flowing down the payment chain.

FreeConsultation Available
BA, JDSite Managed by Ryan Manilla
15+ yrsAt Ontario Bar
Published February 4, 2027Updated February 4, 2027Legally reviewed by Ryan J. Manilla, BA, JD

Key Takeaways

  • Ontario’s Construction Act imposes strict, legislated timelines for paying a “proper invoice,” replacing the loose, discretionary payment terms many contracts used to rely on.
  • An owner generally has 28 days to pay a proper invoice in full, or to issue a notice of non-payment disputing some or all of it.
  • Payment obligations flow down the chain — once an owner pays (or is deemed to have accepted an invoice), contractors and subcontractors have their own shorter deadlines to pay the parties below them.
  • A notice of non-payment must be specific about what’s being disputed and why — a vague refusal to pay generally doesn’t satisfy the requirement.
  • Prompt payment rules work alongside, not instead of, holdback and lien rights, forming one connected payment and security framework.
  • Disputes over a proper invoice can be sent to the Construction Act’s fast, interim adjudication process rather than waiting for a full court claim.

Why prompt payment was introduced

Before Ontario’s Construction Act, 2019 introduced prompt payment, payment terms on construction projects were largely left to whatever the contract said — and contracts often gave owners and general contractors considerable discretion over when to pay, sometimes stretching out timelines well beyond what subcontractors and suppliers further down the chain could comfortably absorb. Slow payment at the top of the chain tended to cascade into even slower payment further down, since each party was often waiting to be paid before paying the parties below them.

Prompt payment addresses this by imposing mandatory, legislated deadlines for paying a proper invoice, rather than leaving payment timing entirely up to negotiation. The goal is to keep cash moving through the construction pyramid at a predictable pace, reducing the cash-flow strain that smaller subcontractors and suppliers often absorbed disproportionately under the old, more flexible system.

It’s worth being clear about what prompt payment changes and what it doesn’t. It doesn’t change how much is owed under a contract, and it doesn’t resolve genuine disputes about the quality or completeness of work — what it changes is the process and timing around paying (or formally disputing) an invoice once it’s submitted, so that disagreements get surfaced quickly rather than simply being left unresolved through delay.

The regime was introduced alongside the broader modernization of Ontario’s construction legislation, moving away from the former Construction Lien Act’s framework, which focused mainly on security through liens and holdback without directly addressing how quickly payment itself should move. Prompt payment and the adjudication process that accompanies it fill that gap, targeting the payment process itself rather than only the security available once payment has already failed.

What counts as a proper invoice

The prompt payment clock doesn’t start running from just any bill — it starts from a proper invoice, a term with a specific meaning under the Construction Act. A proper invoice generally needs to include details such as the contractor’s contact and billing information, a description of the services or materials provided, the amount claimed and how it was calculated, and the period the invoice covers, along with any other requirements the contract itself adds.

Getting invoicing right matters more under prompt payment than it may have under older contract practices, because an invoice that’s missing required information may not actually qualify as a proper invoice — which means it may not start the statutory payment clock at all, even if it looks reasonable on its face.

Worth knowing

Contracts can add their own specific invoicing requirements on top of the Construction Act’s baseline, so the precise requirements for a proper invoice can vary somewhat from one project to another.

Contractors submitting invoices, and owners receiving them, both benefit from treating invoicing as more than a bookkeeping formality under this regime. Because an invoice missing required information may not trigger the statutory clock, careful, consistent invoicing practices can matter as much to a contractor’s cash flow as the underlying payment terms themselves.

The payment timelines, step by step

Once a proper invoice is delivered, an owner generally has 28 days to either pay it in full or issue a notice of non-payment disputing some or all of it. Assuming payment is made or deemed accepted, the obligation then flows downward: the contractor generally has a shorter window — often seven days — after being paid to pass along the proportionate share owed to its subcontractors, and subcontractors have their own similarly short deadlines to pay the parties below them in turn.

This cascading structure is the core mechanic of prompt payment. Rather than each party negotiating its own payment terms independently, the statute creates a connected chain of deadlines running from the owner all the way down to the smallest supplier, so that money received at the top is expected to keep moving rather than stalling at any single level.

These timelines are generally treated as minimums that a contract can’t push further out in the owner’s or contractor’s favour, even with the other party’s agreement. A contract can set shorter payment periods than the statutory ones, but it generally can’t extend payment beyond what the Construction Act allows, since that would undercut the point of imposing a mandatory floor in the first place.

Notices of non-payment

If an owner, contractor, or subcontractor disputes all or part of a proper invoice, the Construction Act generally requires a formal notice of non-payment within a specific deadline, rather than simply withholding payment without explanation. The notice has to identify the amount being disputed and the reasons for the dispute, giving the invoicing party a clear basis to respond, negotiate, or escalate the disagreement.

This requirement is meant to prevent payment from being withheld informally or indefinitely. A party that wants to dispute an invoice has to put its reasons on the record within the statutory window, rather than relying on silence or a vague refusal to pay, which the prompt payment regime doesn’t generally treat as a valid response.

A notice of non-payment disputing only part of an invoice doesn’t excuse paying the undisputed portion. Where only a specific line item or amount is genuinely in question, the Construction Act generally expects the undisputed balance to still be paid within the usual timeline, with the dispute narrowed to the specific amount actually being contested.

How this is meant to keep money flowing

The combined effect of proper invoicing requirements, fixed payment deadlines, and required notices of non-payment is meant to replace open-ended payment discretion with a predictable rhythm: invoice, pay or dispute within a set window, and pass funds down the chain within a further set window. Each level of the contract structure is on a clock, rather than waiting indefinitely on the party above it.

Prompt payment doesn’t operate in isolation — it sits alongside holdback requirements (an owner pays a proper invoice promptly, minus the required 10% holdback) and lien rights, which remain available as a further layer of security if payment still doesn’t materialize. Together, these form one connected payment and security framework rather than separate, unrelated rules.

For owners and general contractors, this means payment administration on an active project now has real statutory stakes attached to it — tracking when a proper invoice was received, when the 28-day period expires, and whether a notice of non-payment needs to go out, has become a necessary part of running a project rather than an informal, after-the-fact exercise.

What happens when payment is late

If a proper invoice goes unpaid and no valid notice of non-payment is issued within the deadline, the party owed money generally has several options. These can include suspending further work in defined circumstances, registering a construction lien if the relevant deadlines haven’t passed, or referring the dispute to the Construction Act’s interim adjudication process, which is specifically designed to resolve prompt payment disputes faster than conventional litigation.

Prompt payment and adjudication were introduced together for a reason — the strict payment deadlines are far more meaningful when there’s also a fast way to resolve a disagreement about whether an invoice should have been paid. For a broader look at construction contract terms generally, see our article on key construction contract terms, or the construction insights hub. This is general information about how Ontario’s prompt payment rules work, not a calculation of deadlines for a specific invoice or contract.

Smaller homeowner-driven projects can raise their own practical wrinkles under this framework, since a homeowner acting as owner may be less familiar with proper invoice requirements and statutory deadlines than a commercial owner with dedicated project administration. Our article on homeowner-contractor disputes touches on some of these practical dynamics in more detail.

Legally reviewed by Ryan J. Manilla, BA, JDGeneral legal information, not personalized legal advice.Read our review policy →

More in Construction

Continue reading

Construction

Construction Contracts in Ontario: Key Terms to Know

Walks through what a solid construction contract should cover — scope, price and payment schedule, change orders, holdback, substantial performance, warranty and dispute resolution — and how CCDC standard forms fit in.

February 1, 2027
Construction

Construction Liens in Ontario: How They Work and Filing Deadlines

What a construction lien secures, who can claim one, Ontario’s 60-day preservation and 90-day perfection deadlines, and what registering a lien does to title.

February 2, 2027
Construction

Holdback Requirements Under Ontario’s Construction Act

Covers the mandatory 10% holdback, why it exists, basic versus finishing holdback, when it becomes releasable, and annual or phased release on longer projects.

February 3, 2027
Construction

Interim Adjudication for Ontario Construction Disputes

Explains the fast interim adjudication process under the Construction Act — which disputes qualify, how notice and appointment work, the 30-day decision timeline, and how it differs from mediation, arbitration and litigation.

February 5, 2027
Construction

Home Renovation Contracts in Ontario: What to Include

Key terms every homeowner-renovator contract should cover — scope, pricing, milestone-based payment, permits, change orders, cleanup and warranty — plus red flags to watch for.

February 6, 2027
Construction

Subcontractor Agreements in Ontario

What a general contractor–subcontractor agreement should cover, including pay-when-paid versus pay-if-paid clauses, prompt payment, insurance and indemnities, and the lien rights subcontractors keep regardless of contract wording.

February 7, 2027
Construction

Construction Deficiency Claims in Ontario

How to tell a deficiency from normal wear, document it properly, use holdback as leverage, and the options available when a contractor won’t fix defective work.

February 8, 2027
Construction

Substantial Performance in Ontario Construction Projects

What substantial performance means under the Construction Act, how it’s determined, and why publishing a certificate starts lien deadlines and can trigger holdback release.

February 9, 2027
Construction

Change Orders in Ontario Construction Contracts

Explains why scope changes need a written change order rather than a verbal instruction, covering price, schedule and holdback impacts, the typical approval process, and the risks unrecorded extras create for owners and contractors alike.

February 10, 2027
Construction

Performance and Labour & Material Bonds in Ontario

Breaks down what a performance bond protects versus a labour and material payment bond, when bonding is typically required, and how a bond claim against the surety generally proceeds.

February 11, 2027
Construction

Discharging or Vacating a Construction Lien in Ontario

Walks through an owner’s options when facing a registered lien — paying it out, negotiating a holdback-based arrangement, or posting security to vacate the lien from title — plus what happens when a claimant misses the Construction Act’s deadlines.

February 12, 2027
Construction

Homeowner vs. Contractor Disputes in Ontario

Covers common flashpoints such as incomplete work, overruns, delays and quality, practical first steps, holdback and lien dynamics from the homeowner’s side, and escalation through Small Claims or Superior Court.

February 13, 2027

FAQ

Frequently asked questions

What is prompt payment under Ontario’s Construction Act?+

Prompt payment is a set of mandatory timelines the Construction Act imposes for paying a proper invoice submitted under a construction contract. It replaced the more informal, often lengthy payment terms many construction contracts used to include, with the goal of keeping money moving down the contract chain more predictably.

What counts as a “proper invoice” in Ontario construction law?+

A proper invoice is a written bill for work or materials that meets the specific requirements set out in the Construction Act and the contract — generally including the contractor’s information, a description of the work, the amount claimed, and the period it covers. An invoice that doesn’t meet these requirements may not start the statutory payment clock.

How long does an owner have to pay a proper invoice in Ontario?+

An owner generally has 28 days after receiving a proper invoice to pay it in full, or to issue a valid notice of non-payment disputing some or all of the amount claimed. This timeline runs regardless of a contract’s own payment terms if those terms are less favourable than the statutory minimum.

What is a notice of non-payment?+

A notice of non-payment is a formal written notice an owner, contractor, or subcontractor issues within a specific statutory deadline to dispute all or part of a proper invoice. It must identify the amount being disputed and give reasons, rather than simply stating that payment won’t be made.

What happens if an owner doesn’t pay or issue a notice of non-payment in time?+

If the deadline passes without payment or a valid notice of non-payment, the contractor may be entitled to treat the invoiced amount as owing and pursue remedies, including suspending work in some circumstances or referring the dispute to the Construction Act’s adjudication process.

Do subcontractors benefit from prompt payment rules too?+

Yes. Prompt payment is designed as a chain: once an owner pays (or is deemed to accept) an invoice, the contractor generally has a shorter deadline — often seven days — to pay its subcontractors their proportionate share, and subcontractors have similar downstream deadlines to pay their own subcontractors or suppliers.

Can a contract override the Construction Act’s prompt payment timelines?+

Generally, no. The prompt payment provisions are intended to apply regardless of contrary contract terms, so a clause that tries to extend payment timelines beyond the statutory periods is typically unenforceable to that extent, even if both parties signed it.

What can I do if I’m not being paid on time under the prompt payment rules?+

Options generally include pursuing the adjudication process created alongside prompt payment for a fast, interim decision, registering a construction lien if the applicable deadlines haven’t passed, or pursuing a conventional breach of contract claim. Which option makes sense depends on the amount owing and the urgency of the situation.

Does prompt payment apply to all construction contracts in Ontario?+

Prompt payment generally applies to contracts and subcontracts under the Construction Act for improvements to real property in Ontario, though some government and institutional contracts have specific variations. It’s worth confirming whether a particular project or contract falls within the regime’s scope rather than assuming it automatically does or doesn’t.

What’s the difference between prompt payment and holdback?+

Prompt payment governs the timing of paying proper invoices as work progresses, while holdback is the 10% an owner retains from those payments specifically to fund potential lien claims. They operate together — an owner pays a proper invoice promptly, minus the required holdback — rather than being alternatives to each other.

Can work be suspended for non-payment under Ontario’s Construction Act?+

In some circumstances, yes. If payment isn’t made as required and the statutory conditions are met, a contractor or subcontractor may be entitled to suspend work until payment is made, though this is a significant step with its own notice requirements and risks if applied incorrectly.

How is a prompt payment dispute actually resolved?+

Many prompt payment disputes are resolved through the Construction Act’s interim adjudication process, which is designed to produce a binding (though interim) decision quickly, without waiting for a full court claim. See our article on interim adjudication for more on how that process works in practice.

Understand your agreement. Know your next step.

Ontario-wide, plain-English contract law information — built to help you make sense of your situation before you decide what to do next.

Free Consultation

Speak with a contract lawyer, free of charge

Tell us briefly what’s going on and we’ll be in touch to set up a free consultation about your contract situation.