Substantial Performance in Ontario Construction Projects

What substantial performance means under the Construction Act, how it’s determined, and why publishing a certificate starts lien deadlines and can trigger holdback release.

FreeConsultation Available
BA, JDSite Managed by Ryan Manilla
15+ yrsAt Ontario Bar
Published February 9, 2027Updated February 9, 2027Legally reviewed by Ryan J. Manilla, BA, JD

Key Takeaways

  • Substantial performance generally means a project is ready to be used for its intended purpose, with only minor items left to finish.
  • It is a defined legal concept under Ontario’s Construction Act, not just a general sense that a project is “mostly done.”
  • Publishing a certificate of substantial performance starts the clock on lien preservation deadlines for everyone on the project.
  • It can also trigger the point at which basic holdback becomes eligible for release, separate from any finishing holdback that remains.
  • The certificate is typically issued by the payment certifier, consultant, or owner, and is published through a construction trade newspaper.
  • Getting the timing of substantial performance wrong can shorten or extend lien deadlines unexpectedly for contractors and subcontractors alike.

What “substantial performance” means

Substantial performance is a defined concept under Ontario’s Construction Act, not just an informal sense that a project is “mostly done.” It generally refers to the point at which the work under a contract — or a defined part of it — is far enough along that the owner can use the improvement for its intended purpose, with only minor items left outstanding. Those outstanding items are typically small finishing touches or minor deficiencies, not anything that would prevent normal use of the space.

It is worth distinguishing substantial performance from full completion. Completion refers to the point at which all of the work, including those remaining minor items, is actually finished. Both milestones matter under the Construction Act, and each triggers its own set of deadlines and holdback consequences, which is why the distinction is more than a matter of wording.

The concept exists because construction projects rarely finish in one clean step. A new building might be ready for an owner to move in and start operating while a handful of finishing touches — a touch-up of paint, a piece of trim, a final inspection sign-off on a minor system — are still outstanding. Treating that kind of project as entirely unfinished until every last item is done would delay payment and lien timelines well past the point where the project is actually serving its purpose, which is the practical problem the substantial performance concept is designed to solve.

How substantial performance is determined

On larger or more formally structured projects, a payment certifier or consultant named in the contract — often an architect or engineer — is typically responsible for assessing whether the statutory test for substantial performance has been met and issuing a certificate confirming it. On smaller projects, including many residential renovations, there is often no named certifier, in which case the owner generally makes this determination, sometimes with input from the contractor, applying the same statutory test.

The assessment generally focuses on whether the project can be used for the purpose it was intended for, with the value of any remaining work weighed against the overall contract price. A project with extensive work still outstanding, or with issues that genuinely prevent normal use, has likely not reached substantial performance under the Act, regardless of how the parties might informally describe it.

Because the determination carries real financial consequences for everyone on the project, it is not simply a matter of the owner or certifier declaring the project finished enough. The statutory test looks at concrete factors, including the proportion of the contract price represented by any outstanding work, so a certificate issued on flimsy grounds can later be challenged by a contractor or subcontractor whose lien deadlines were affected by it.

Why publishing a certificate matters

Publishing a certificate of substantial performance is far more than a formality — it is the event that starts statutory lien preservation deadlines running for everyone connected to the relevant scope of work. Under the Construction Act, those involved generally have 60 days from the publication date to preserve a lien connected to that portion of the project, and a further 90 days after that to perfect it.

Publication date, not private notice

The relevant deadline generally runs from the date the certificate is published in a qualifying construction trade newspaper, not from when a contractor or subcontractor happens to find out about it informally. Confirming the actual publication date is usually the first step in figuring out where a project stands on its lien timeline. See our guide to construction liens in Ontario for the fuller timeline.

Because the publication date carries so much weight, confirming whether — and when — a certificate was actually published is often one of the first things worth checking when a question arises about lien deadlines on a project nearing the end of its work.

This matters just as much for parties who were not directly involved in determining substantial performance. A subcontractor or supplier whose own work wrapped up weeks or months earlier can still find its lien deadline tied to a publication date set by a certifier assessing the project as a whole, which is one reason it is worth checking in on this milestone periodically as a project nears its end, rather than assuming a personal completion date is the only clock running.

How a certificate is published

The Construction Act requires that a certificate of substantial performance be published in a construction trade newspaper that meets the Act’s specific criteria for this purpose. This creates a dateable, public record that lien deadlines can be measured against, rather than relying on private correspondence between the parties, which could otherwise create disputes about exactly when notice was given.

In practice, copies of a published certificate are also typically made available by the payment certifier, consultant, owner, or general contractor responsible for the project, so a contractor or subcontractor wanting to confirm the date can usually request it directly rather than relying only on the trade publication itself.

For a project without a formal certifier, the parties may still need to document that substantial performance was reached and when, even without going through the formal trade publication process in every case. Clear written confirmation between the owner and contractor of the date the project became ready for use can help avoid later disagreement over when the relevant deadlines actually began to run.

How substantial performance connects to holdback release

Substantial performance also connects directly to holdback. Once the lien preservation period following publication of the certificate has passed without liens being preserved against the relevant holdback — or once any liens that were preserved have been dealt with — the basic holdback tied to the substantially performed work generally becomes eligible for release to the contractor.

Any separate holdback tied to finishing the remaining minor items, sometimes called finishing holdback, generally stays tied to full completion of that remaining work rather than to the substantial performance date. This two-stage structure is part of why substantial performance and completion are tracked as distinct milestones rather than a single event. Our guide to holdback requirements in Ontario walks through the release mechanics in more depth.

In practice, this means a contractor can generally expect two separate payment events after a project wraps up: the basic holdback becoming available once the lien preservation window tied to substantial performance closes, and the finishing holdback becoming available only once the last outstanding items are actually completed to the owner’s satisfaction. Treating these as one combined release date is a common source of confusion between owners and contractors near the end of a project.

Next steps

For anyone involved in a project approaching its final stages — owners, general contractors, and subcontractors alike — it is generally worth confirming directly with the payment certifier, consultant, or owner whether a certificate of substantial performance has been issued, and if so, when it was or will be published. That date becomes the reference point for lien deadlines and holdback release that follow.

Where a dispute arises over the timing or accuracy of a substantial performance determination, our guides to construction adjudication in Ontario and construction liens explain the processes available to address it. This article is general information about how substantial performance generally works under Ontario’s Construction Act, not legal advice for a specific project — our contact page can help point toward further resources.

Legally reviewed by Ryan J. Manilla, BA, JDGeneral legal information, not personalized legal advice.Read our review policy →

More in Construction

Continue reading

Construction

Construction Contracts in Ontario: Key Terms to Know

Walks through what a solid construction contract should cover — scope, price and payment schedule, change orders, holdback, substantial performance, warranty and dispute resolution — and how CCDC standard forms fit in.

February 1, 2027
Construction

Construction Liens in Ontario: How They Work and Filing Deadlines

What a construction lien secures, who can claim one, Ontario’s 60-day preservation and 90-day perfection deadlines, and what registering a lien does to title.

February 2, 2027
Construction

Holdback Requirements Under Ontario’s Construction Act

Covers the mandatory 10% holdback, why it exists, basic versus finishing holdback, when it becomes releasable, and annual or phased release on longer projects.

February 3, 2027
Construction

Prompt Payment Rules in Ontario Construction Contracts

Covers the proper invoice requirement, the cascading 28-day and 7-day payment timelines, notices of non-payment, and how the regime is meant to keep money flowing down the payment chain.

February 4, 2027
Construction

Interim Adjudication for Ontario Construction Disputes

Explains the fast interim adjudication process under the Construction Act — which disputes qualify, how notice and appointment work, the 30-day decision timeline, and how it differs from mediation, arbitration and litigation.

February 5, 2027
Construction

Home Renovation Contracts in Ontario: What to Include

Key terms every homeowner-renovator contract should cover — scope, pricing, milestone-based payment, permits, change orders, cleanup and warranty — plus red flags to watch for.

February 6, 2027
Construction

Subcontractor Agreements in Ontario

What a general contractor–subcontractor agreement should cover, including pay-when-paid versus pay-if-paid clauses, prompt payment, insurance and indemnities, and the lien rights subcontractors keep regardless of contract wording.

February 7, 2027
Construction

Construction Deficiency Claims in Ontario

How to tell a deficiency from normal wear, document it properly, use holdback as leverage, and the options available when a contractor won’t fix defective work.

February 8, 2027
Construction

Change Orders in Ontario Construction Contracts

Explains why scope changes need a written change order rather than a verbal instruction, covering price, schedule and holdback impacts, the typical approval process, and the risks unrecorded extras create for owners and contractors alike.

February 10, 2027
Construction

Performance and Labour & Material Bonds in Ontario

Breaks down what a performance bond protects versus a labour and material payment bond, when bonding is typically required, and how a bond claim against the surety generally proceeds.

February 11, 2027
Construction

Discharging or Vacating a Construction Lien in Ontario

Walks through an owner’s options when facing a registered lien — paying it out, negotiating a holdback-based arrangement, or posting security to vacate the lien from title — plus what happens when a claimant misses the Construction Act’s deadlines.

February 12, 2027
Construction

Homeowner vs. Contractor Disputes in Ontario

Covers common flashpoints such as incomplete work, overruns, delays and quality, practical first steps, holdback and lien dynamics from the homeowner’s side, and escalation through Small Claims or Superior Court.

February 13, 2027

FAQ

Frequently asked questions

What does “substantial performance” mean under Ontario’s Construction Act?+

Substantial performance generally means the work, or a defined phase of it, is far enough along that the owner can use the improvement for its intended purpose, with only minor finishing items — sometimes called deficiencies or outstanding items — left to complete. The Construction Act sets out a specific test for when this point is reached, rather than leaving it to informal judgment alone.

Is substantial performance the same as completion?+

No. Substantial performance is reached before full completion and generally focuses on whether the project is ready for its intended use, while completion refers to the point at which all work, including minor finishing items, is actually finished. Both concepts matter under the Construction Act, but they trigger different deadlines and holdback releases.

Who decides when a construction project has reached substantial performance?+

On larger projects, a payment certifier or consultant named in the contract typically makes this determination and issues a certificate. On smaller projects without a named certifier, the determination is often made by the owner, sometimes in consultation with the contractor, applying the Construction Act’s statutory test.

Why does publishing a certificate of substantial performance matter so much?+

Publishing the certificate starts the clock on lien preservation deadlines for everyone involved in the project — generally 60 days from the date of publication for parties connected to the portion of work covered by the certificate. Until a certificate is published, those lien deadlines generally have not started running for substantial performance, which makes the publication date a critical reference point.

How is a certificate of substantial performance published in Ontario?+

The Construction Act requires publication in a construction trade newspaper that meets the Act’s criteria, which creates a public, dateable record that lien deadlines can run from. This differs from simply notifying the contractor or subcontractors directly, since the statutory deadline is tied to the publication date, not to private notice.

Does substantial performance affect holdback release?+

Yes. Once the lien preservation period following publication of the certificate has passed without liens being preserved (or once any preserved liens are dealt with), the basic holdback tied to the substantially performed work generally becomes eligible for release. Any separate finishing or completion holdback remains tied to full completion of the remaining work.

What happens if no certificate of substantial performance is ever published?+

If a certificate is never issued, the statutory lien deadlines tied to publication do not start running from that event, though other triggering events under the Construction Act — such as completion or abandonment of the contract, or last supply of services or materials — can still start the clock independently. This is one reason it is worth confirming whether a certificate was published rather than assuming deadlines have not yet begun.

Can a project be substantially performed but still have significant work outstanding?+

Generally no, not in the sense the Act intends. The outstanding items are meant to be minor — things that do not prevent the owner from using the project for its intended purpose. If the remaining work is extensive or prevents normal use, the project likely has not actually reached substantial performance, regardless of what a certificate claims.

Who can dispute a certificate of substantial performance?+

A contractor, subcontractor, or supplier who disagrees with the determination — for example, believing the project was declared substantially performed prematurely, or not declared when it should have been — may raise the issue, and in some cases this can become the subject of an adjudication or court proceeding, since the timing has real financial consequences for lien rights and holdback.

Does substantial performance apply separately to each phase of a large project?+

It can. The Construction Act allows for substantial performance to be determined for a defined phase or segment of a contract in some circumstances, which can mean different parts of a large project reach substantial performance — and trigger their own lien deadlines and holdback releases — at different times.

How does substantial performance affect subcontractors specifically?+

Publication of a certificate covering the head contract generally starts lien preservation deadlines running for the general contractor and often for subcontractors connected to that scope of work as well, even though the subcontractor’s own work may have finished earlier or later. Subcontractors are generally well served by tracking the publication date closely rather than relying only on their own completion date.

Where can I find a published certificate of substantial performance for a project?+

Certificates are published in a construction trade newspaper meeting the Construction Act’s requirements, and copies are also typically available from the payment certifier, consultant, owner, or general contractor responsible for the project. Checking directly with the party responsible for the contract is usually the most reliable way to confirm whether, and when, a certificate was published.

Understand your agreement. Know your next step.

Ontario-wide, plain-English contract law information — built to help you make sense of your situation before you decide what to do next.

Free Consultation

Speak with a contract lawyer, free of charge

Tell us briefly what’s going on and we’ll be in touch to set up a free consultation about your contract situation.