Change Orders in Ontario Construction Contracts
Explains why scope changes need a written change order rather than a verbal instruction, covering price, schedule and holdback impacts, the typical approval process, and the risks unrecorded extras create for owners and contractors alike.
Key Takeaways
- A change order records an agreed adjustment to scope, price, or schedule — it is not optional paperwork, it is the record of what the contract actually became.
- Verbal “just do it” instructions are common on site, but they create real evidence problems if the owner and contractor later disagree about price.
- Unrecorded extras can distort the final contract price used to calculate the 10% holdback and any lien amount under Ontario’s Construction Act, 2019.
- A typical change order process includes a written description of the change, a price and schedule impact, and a signature from both sides before work proceeds.
- Contractors who perform extra work without a signed change order risk not getting paid for it, even if the owner clearly asked for the work verbally.
- Owners who approve changes informally risk a final invoice that is much higher than expected, with little paper trail to dispute it.
What is a change order?
A change order is simply a written record of a change to the deal — a change in scope (adding, removing, or altering work), a change in price, a change in schedule, or some mix of all three. On almost every construction project of any size, the work actually performed ends up differing at least a little from the original drawings and specifications, whether that is because the owner wants an upgrade, an unexpected condition turns up behind a wall, or a supply issue forces a substitution. The change order is the mechanism that keeps the contract matching reality.
In practice, a change order is usually a short document that describes the change, sets out the price adjustment (an increase, a decrease, or sometimes a credit), notes any effect on the schedule, and is signed by both the owner (or an authorized representative, like a general contractor or payment certifier) and the contractor performing the work. Once signed, it generally becomes part of the contract, adjusting the original contract price going forward.
For background on how the underlying agreement is usually structured before any changes come up, see our overview of construction contracts in Ontario.
Why scope changes need to be documented
It is tempting, especially on a fast-moving job site, to treat a scope change as a quick conversation rather than paperwork. The owner asks for an extra outlet, the contractor says sure, and both move on. The trouble is that “sure” does not say what the extra outlet costs, whether it affects the schedule, or who is responsible if it turns out to be more complicated than expected once the wall is opened up.
Documenting a change in writing, even briefly, does three things. First, it fixes the price before the work is done, rather than leaving it to be negotiated after the fact when neither side has much leverage to disagree. Second, it creates a record that can be checked against the final invoice, the project schedule, and — if it ever comes to this — a lien claim or a court proceeding. Third, it protects both sides: the contractor is protected against doing free work it never gets paid for, and the owner is protected against being billed for work it never actually authorized.
A short note is still documentation
How a typical change order process works
Most well-run projects follow a broadly similar sequence once a potential change comes up. Someone — often the contractor, but sometimes the owner, an architect, or a consultant — identifies that the work needs to differ from what was originally agreed. That person prepares a written description of the proposed change along with a price and schedule estimate, sometimes called a change order request or a proposed change notice.
The owner (or its representative) then reviews the proposed change and either approves it, rejects it, or asks for a revised price. Once both sides agree on the terms, the change order is signed, and the changed work is authorized to proceed on those terms. Many standard-form contracts require this approval before the contractor is obligated to perform the extra work, which gives the contractor a reasonable basis to pause rather than start on a change that has not yet been priced.
On larger or public projects, this process is often formalized with numbered change order logs, so both sides can track every change against the original contract price and see, at a glance, how far the total price has moved from the original number.
Timing also matters. A change order agreed before the changed work starts gives both sides a clear baseline to work from, while one negotiated after the work is already done tends to involve more friction, since the contractor has less incentive to accept a lower price once the work is complete and the owner has less incentive to pay more than it expected. Where circumstances genuinely require work to start before pricing is finalized — an urgent repair, for instance — many contracts allow the owner to issue a change directive authorizing the work to proceed while price and schedule impacts are worked out shortly afterward, rather than leaving the instruction entirely informal.
Lien and holdback implications of unrecorded extras
Ontario’s Construction Act, 2019 ties several important deadlines and obligations to the contract price, which makes accurate documentation of changes more than just good bookkeeping. Holdback — generally 10% of the value of services or materials supplied — is calculated against the price of the contract as it stands, so if extras are left undocumented, it can become genuinely unclear what number the holdback should be based on. For a closer look at how holdback actually works, see our guide to holdback requirements in Ontario.
Lien rights are also affected. A lien claim is generally limited to the value of the services or materials actually supplied and unpaid for, and unrecorded extra work can make it harder for a contractor to establish the amount it is entitled to claim if a dispute ends up at the registry. For background on how liens work more generally, including the preservation and perfection deadlines under the Act, see our guide to construction liens in Ontario.
Properly documented change orders also matter for the prompt payment and adjudication regime introduced by the Act, since a proper invoice generally needs to reflect the agreed contract price, including authorized changes, in order to start the clock on payment deadlines. See our overview of prompt payment in Ontario for more detail.
Risks of verbal “just do it” changes
For the contractor, performing work on a verbal instruction alone carries a real risk of not getting paid for it, or getting paid less than expected. If the owner later disputes that the instruction was given, disputes the scope of what was asked for, or disputes the price, the contractor is left trying to prove an oral conversation rather than pointing to a signed document. Even where a court is ultimately persuaded that work was requested and performed, pursuing that claim takes time, cost, and uncertainty that a signed change order would have avoided entirely.
For the owner, the risk runs the other way. A string of verbal “just do it” approvals can add up to a significant increase in the final price with no clear record of what was agreed to at each step. This is a common source of frustration on residential renovation projects in particular, where an owner says yes to small changes one at a time without tracking the cumulative cost, only to be surprised by the final invoice.
Both risks point the same direction: a quick written confirmation, even an informal one, protects whoever is relying on it. Neither party benefits, over the life of a project, from leaving scope changes undocumented.
If a change order dispute arises
When a disagreement about extra work does come up, the first practical step is usually to gather whatever record exists — emails, texts, site meeting notes, photographs of the work, and any partial documentation — even if a formal change order was never signed. This record often ends up being the main evidence of what was actually agreed, so it is worth assembling it carefully rather than relying on memory.
Many change order disputes get resolved through direct negotiation once both sides lay out their documentation side by side. Where that does not resolve things, options generally include adjudication under the Construction Act for payment disputes on an eligible contract (see our guide to construction adjudication in Ontario), a lien claim if the amount owing relates to unpaid services or materials, or a claim in Small Claims Court or the Superior Court of Justice depending on the amount involved.
This article provides general information about how change orders generally work in Ontario construction projects and is not legal advice about any specific project or dispute. Our tools and contact page may be useful starting points for further research.
More in Construction
Continue reading
Construction Contracts in Ontario: Key Terms to Know
Walks through what a solid construction contract should cover — scope, price and payment schedule, change orders, holdback, substantial performance, warranty and dispute resolution — and how CCDC standard forms fit in.
Construction Liens in Ontario: How They Work and Filing Deadlines
What a construction lien secures, who can claim one, Ontario’s 60-day preservation and 90-day perfection deadlines, and what registering a lien does to title.
Holdback Requirements Under Ontario’s Construction Act
Covers the mandatory 10% holdback, why it exists, basic versus finishing holdback, when it becomes releasable, and annual or phased release on longer projects.
Prompt Payment Rules in Ontario Construction Contracts
Covers the proper invoice requirement, the cascading 28-day and 7-day payment timelines, notices of non-payment, and how the regime is meant to keep money flowing down the payment chain.
Interim Adjudication for Ontario Construction Disputes
Explains the fast interim adjudication process under the Construction Act — which disputes qualify, how notice and appointment work, the 30-day decision timeline, and how it differs from mediation, arbitration and litigation.
Home Renovation Contracts in Ontario: What to Include
Key terms every homeowner-renovator contract should cover — scope, pricing, milestone-based payment, permits, change orders, cleanup and warranty — plus red flags to watch for.
Subcontractor Agreements in Ontario
What a general contractor–subcontractor agreement should cover, including pay-when-paid versus pay-if-paid clauses, prompt payment, insurance and indemnities, and the lien rights subcontractors keep regardless of contract wording.
Construction Deficiency Claims in Ontario
How to tell a deficiency from normal wear, document it properly, use holdback as leverage, and the options available when a contractor won’t fix defective work.
Substantial Performance in Ontario Construction Projects
What substantial performance means under the Construction Act, how it’s determined, and why publishing a certificate starts lien deadlines and can trigger holdback release.
Performance and Labour & Material Bonds in Ontario
Breaks down what a performance bond protects versus a labour and material payment bond, when bonding is typically required, and how a bond claim against the surety generally proceeds.
Discharging or Vacating a Construction Lien in Ontario
Walks through an owner’s options when facing a registered lien — paying it out, negotiating a holdback-based arrangement, or posting security to vacate the lien from title — plus what happens when a claimant misses the Construction Act’s deadlines.
Homeowner vs. Contractor Disputes in Ontario
Covers common flashpoints such as incomplete work, overruns, delays and quality, practical first steps, holdback and lien dynamics from the homeowner’s side, and escalation through Small Claims or Superior Court.
FAQ
Frequently asked questions
What is a change order in an Ontario construction contract?
A change order is a written document that records an agreed change to the scope of work, the contract price, the schedule, or some combination of the three. It is typically signed by both the owner (or their representative) and the contractor before the changed work proceeds, and it becomes part of the overall contract once executed.
Is a verbal change order legally binding in Ontario?
A verbal agreement to change the work can, in principle, still be enforceable, since Ontario generally allows oral contracts and oral amendments. The practical problem is proof — without anything in writing, it becomes much harder to show what was actually agreed about price, scope, or timing if the parties later disagree.
Can a contractor refuse to do extra work without a signed change order?
Generally, yes. Most construction contracts require extra or changed work to go through a defined change order process before the contractor is obligated to proceed, and a contractor can usually decline to start additional work until the price and scope are documented and approved.
What happens if extra work is done but never documented in a change order?
The contractor may still be able to pursue payment for work it can show was requested and performed, often through a claim for the reasonable value of the work rather than a straightforward contract claim. This is a much harder and less predictable path than simply pointing to a signed change order, which is why documentation matters so much in practice.
Do change orders affect the 10% holdback under the Construction Act?
Yes. Holdback is calculated as a percentage of the contract price, and unrecorded or disputed extras can make it unclear what the “contract price” actually is at any given point. A clear paper trail of change orders helps everyone calculate holdback and any potential lien amount accurately as the project proceeds.
Who typically pays for a change order on a construction project?
This depends entirely on the contract and the nature of the change. A change requested by the owner (adding a feature, upgrading a finish) is usually billed to the owner, while a change needed to correct the contractor’s own error is generally not. Changes triggered by unforeseen site conditions or regulatory requirements are often the subject of specific contract clauses addressing who bears that cost.
Can a change order extend the project schedule in Ontario?
Yes, a change order can adjust the completion date in addition to price, and many standard change order forms include a schedule impact field for exactly this reason. Extending the schedule through a documented change order is generally preferable to an informal understanding, since schedule disputes are common later in a project.
What should a homeowner do if a contractor asks for more money mid-project without a change order?
This is a common flashpoint in residential projects, and asking for a written breakdown of the additional cost before agreeing or paying is a reasonable general practice. Requesting that any agreed change be documented, even briefly in an email or text, helps avoid confusion about the final price later.
Does a verbal change order instruction count as a “triggering event” for lien purposes?
The Construction Act’s lien preservation deadlines generally run from events like substantial performance, completion, abandonment, or the last supply of services or materials — not from the date of a verbal instruction itself. However, undocumented extra work can still complicate figuring out exactly when supply of services or materials under the contract actually ended.
Can a change order be rejected or disputed after it is signed?
Once both parties sign a change order, it generally becomes a binding part of the contract and is difficult to unwind without agreement or a legitimate legal basis, such as misrepresentation. This is one reason it is worth reviewing the scope, price, and schedule impact carefully before signing rather than after the fact.
Is there a standard change order form used in Ontario?
There is no single mandatory form, but many standard-form construction contracts (including widely used CCDC documents) include their own change order or change directive templates. Owners and contractors using a custom contract can still adopt a simple written format covering scope, price, and schedule as long as both sides sign off.
What is the difference between a change order and a change directive?
A change order is typically a fully agreed document signed by both parties before work proceeds. A change directive is generally used when an owner wants work to proceed urgently and the parties have not yet agreed on price or schedule impact, with those details worked out afterward — some standard-form contracts specifically provide for this distinction.