Holdback Requirements Under Ontario’s Construction Act

Covers the mandatory 10% holdback, why it exists, basic versus finishing holdback, when it becomes releasable, and annual or phased release on longer projects.

FreeConsultation Available
BA, JDSite Managed by Ryan Manilla
15+ yrsAt Ontario Bar
Published February 3, 2027Updated February 3, 2027Legally reviewed by Ryan J. Manilla, BA, JD

Key Takeaways

  • Ontario’s Construction Act requires owners to hold back 10% of the contract price from payments to the contractor on most projects.
  • Holdback exists mainly to fund potential construction lien claims by subcontractors, suppliers, and workers further down the contract chain.
  • “Basic holdback” covers the general lien period, while “finishing holdback” can apply to specific, substantially completed phases of a larger project.
  • Holdback generally becomes releasable once the relevant lien period expires without a lien being preserved — it isn’t simply paid out automatically.
  • Large, multi-year projects can sometimes use annual or phased holdback release instead of holding back 10% of the entire contract until the very end.
  • Releasing holdback early or incorrectly can leave an owner personally exposed to unpaid subcontractors and suppliers who still have lien rights.

What holdback is

Holdback is money an owner is required to retain from payments otherwise owed to a contractor under a construction contract. Ontario’s Construction Act sets the amount at 10% of the value of services or materials supplied, calculated before HST, and the requirement applies on most projects regardless of what the contract between the parties says.

In practice, this means that if a contractor invoices $100,000 for work completed to date, the owner is generally required to pay out only $90,000 at that time, retaining $10,000 as holdback. The same 10% retention applies again as the contractor (or subcontractor) makes its own payments further down the chain, so holdback accumulates at every level of the contract structure, not just at the top.

Holdback is calculated on the value of services and materials actually supplied, not on the full original contract price if the scope has changed. Where change orders increase or decrease the contract price, the holdback calculation generally follows the updated value of work actually performed, which is one more reason accurate, up-to-date invoicing matters on an active project.

Why holdback exists

The purpose of holdback is closely tied to construction lien rights. Because subcontractors, suppliers, and workers can register a lien against a property if they aren’t paid for work or materials they supplied, the Construction Act requires owners to keep a portion of each payment in reserve, specifically so there’s a known fund available to satisfy lien claims if they arise.

Without a holdback requirement, an owner could pay a general contractor in full, the general contractor could fail to pay its subcontractors, and those subcontractors would have far less practical ability to recover what they’re owed — even though they have lien rights in theory. Holdback is meant to make sure a meaningful fund actually exists for that purpose, rather than leaving lien rights as a right without a reliable source of money behind them.

Worth knowing

Holdback isn’t a penalty or a sign of distrust toward the contractor — it’s a statutory requirement that applies to every qualifying project, regardless of how the relationship between the owner and contractor is going.

Holdback also indirectly supports Ontario’s prompt payment regime, since the Construction Act’s overall structure assumes that payment flows down the contract chain reasonably quickly, with holdback as the backstop for the portion that’s deliberately retained rather than a reason to withhold payment more broadly than the statute allows.

Basic holdback vs. finishing holdback

Basic holdback is the general 10% retained against the overall contract price, tied to the standard lien period that runs from the relevant triggering event for the project as a whole, such as the publication of a certificate of substantial performance.

Finishing holdback is a related but distinct concept that can apply once a defined portion of the contract — sometimes called a phase, or the remaining work after substantial performance — is itself completed. Finishing holdback allows the holdback tied specifically to that finishing work to be assessed and potentially released on its own timeline, rather than being bundled automatically with the basic holdback for the rest of the project. The distinction matters mainly on larger projects where different parts of the work reach completion at meaningfully different times.

On a smaller residential project, basic and finishing holdback often end up being released close together, since the whole job reaches substantial performance at roughly the same time. On larger commercial or multi-phase projects, tracking the two separately can matter a great deal, since it affects when funds tied to an earlier, completed phase actually become available rather than staying tied up until the whole project wraps up.

When holdback can be released

Holdback doesn’t simply become payable on a fixed date written into the contract — it generally becomes releasable once the applicable lien period has expired without a lien being preserved, or once any liens that were registered have been resolved. Because lien periods are generally tied to events like last supply of services or materials, or publication of a certificate of substantial performance, the release of holdback is tied to the same triggering events as the lien deadlines themselves.

This connection to lien deadlines is deliberate rather than incidental. If holdback could be released before the lien period runs out, a lien claimant could end up with a valid, perfected lien but no fund left for it to actually reach, which would defeat much of the point of requiring holdback in the first place. Linking the two timelines keeps the security meaningful for as long as a lien could still be validly brought.

In practice, this means an owner (or a contractor holding back from a subcontractor) generally needs to track the same dates relevant to lien preservation before releasing holdback, since paying it out too early — while a lien could still be validly preserved — can create personal liability.

On larger projects, a payment certifier such as an architect or engineer named in the contract often confirms the relevant dates and amounts before holdback is released, adding a layer of verification on top of the owner’s own records. On smaller residential jobs without a formal certifier, the owner and contractor are generally left to track these dates themselves, which makes keeping a clear paper trail of invoices, payments, and key project milestones especially useful.

Phased and annual release on longer projects

Holding back 10% of the full contract price for the entire duration of a large, multi-year project can tie up significant funds for a long time. The Construction Act addresses this by allowing certain large projects to use annual or phased release of holdback, so that holdback accumulated during an earlier period of the work can be assessed and released without waiting for the entire project to reach completion.

These mechanisms come with their own specific conditions, notice requirements, and publication steps, and they don’t apply automatically — they generally need to be set up and followed correctly to be effective. Owners and contractors on long-running projects often build these release points into the project schedule from the outset, rather than deciding partway through that phased release would be convenient.

Whether phased release is worthwhile on a given project usually comes down to the size of the contract and how long it runs. On a project lasting many months or years, the cost of tying up a growing holdback balance for the full duration can be significant, which is part of why the Construction Act built in a way to release some of it earlier rather than requiring every dollar to wait for final completion across the whole contract.

What happens when holdback is handled incorrectly

Mishandling holdback is one of the more common and costly mistakes made on Ontario construction projects. Releasing holdback before the applicable lien period has expired, miscalculating the 10% amount, or failing to retain holdback at all can expose an owner to paying twice — once to the general contractor, and again to an unpaid subcontractor or supplier who still has valid lien rights against the property.

Holdback questions often surface alongside broader disputes about payment timing, which is also addressed by the Construction Act’s prompt payment rules, and alongside lien claims themselves. For a general overview of what a construction contract should address, including holdback, see our article on key contract terms, or visit the construction insights hub for more. This is general information about how holdback generally works under Ontario law, not a calculation of what should be held back on any specific project.

Legally reviewed by Ryan J. Manilla, BA, JDGeneral legal information, not personalized legal advice.Read our review policy →

More in Construction

Continue reading

Construction

Construction Contracts in Ontario: Key Terms to Know

Walks through what a solid construction contract should cover — scope, price and payment schedule, change orders, holdback, substantial performance, warranty and dispute resolution — and how CCDC standard forms fit in.

February 1, 2027
Construction

Construction Liens in Ontario: How They Work and Filing Deadlines

What a construction lien secures, who can claim one, Ontario’s 60-day preservation and 90-day perfection deadlines, and what registering a lien does to title.

February 2, 2027
Construction

Prompt Payment Rules in Ontario Construction Contracts

Covers the proper invoice requirement, the cascading 28-day and 7-day payment timelines, notices of non-payment, and how the regime is meant to keep money flowing down the payment chain.

February 4, 2027
Construction

Interim Adjudication for Ontario Construction Disputes

Explains the fast interim adjudication process under the Construction Act — which disputes qualify, how notice and appointment work, the 30-day decision timeline, and how it differs from mediation, arbitration and litigation.

February 5, 2027
Construction

Home Renovation Contracts in Ontario: What to Include

Key terms every homeowner-renovator contract should cover — scope, pricing, milestone-based payment, permits, change orders, cleanup and warranty — plus red flags to watch for.

February 6, 2027
Construction

Subcontractor Agreements in Ontario

What a general contractor–subcontractor agreement should cover, including pay-when-paid versus pay-if-paid clauses, prompt payment, insurance and indemnities, and the lien rights subcontractors keep regardless of contract wording.

February 7, 2027
Construction

Construction Deficiency Claims in Ontario

How to tell a deficiency from normal wear, document it properly, use holdback as leverage, and the options available when a contractor won’t fix defective work.

February 8, 2027
Construction

Substantial Performance in Ontario Construction Projects

What substantial performance means under the Construction Act, how it’s determined, and why publishing a certificate starts lien deadlines and can trigger holdback release.

February 9, 2027
Construction

Change Orders in Ontario Construction Contracts

Explains why scope changes need a written change order rather than a verbal instruction, covering price, schedule and holdback impacts, the typical approval process, and the risks unrecorded extras create for owners and contractors alike.

February 10, 2027
Construction

Performance and Labour & Material Bonds in Ontario

Breaks down what a performance bond protects versus a labour and material payment bond, when bonding is typically required, and how a bond claim against the surety generally proceeds.

February 11, 2027
Construction

Discharging or Vacating a Construction Lien in Ontario

Walks through an owner’s options when facing a registered lien — paying it out, negotiating a holdback-based arrangement, or posting security to vacate the lien from title — plus what happens when a claimant misses the Construction Act’s deadlines.

February 12, 2027
Construction

Homeowner vs. Contractor Disputes in Ontario

Covers common flashpoints such as incomplete work, overruns, delays and quality, practical first steps, holdback and lien dynamics from the homeowner’s side, and escalation through Small Claims or Superior Court.

February 13, 2027

FAQ

Frequently asked questions

How much holdback is required on a construction project in Ontario?+

Ontario’s Construction Act generally requires owners to hold back 10% of the value of services or materials supplied under a contract, calculated before HST, from each payment made to the contractor. This 10% figure is a statutory minimum and applies regardless of what the contract between the parties says.

Why does Ontario require a construction holdback?+

Holdback exists primarily to fund potential lien claims. Because subcontractors, suppliers, and workers can register a construction lien against the property if they aren’t paid, the holdback retained by the owner is generally meant to be the fund those lien claims can reach, rather than relying only on the general contractor’s own finances.

Can a contract waive or reduce the 10% holdback requirement?+

No. The holdback obligation is a minimum set by statute, and a contract generally can’t contract out of it or reduce the percentage below 10%. Parties can agree on additional terms around timing and process, but the underlying obligation to retain the holdback amount isn’t something a private agreement can remove.

When can holdback be released to the contractor?+

Holdback generally becomes releasable once the relevant lien period has expired without anyone registering a lien, or once any liens that were registered have been satisfied, discharged, or otherwise resolved. It isn’t paid out automatically on a fixed calendar date — it depends on the lien period tied to the applicable triggering event, such as publication of a certificate of substantial performance.

What’s the difference between basic holdback and finishing holdback?+

Basic holdback is the general 10% retained against the whole contract price and covers the standard lien period for the project. Finishing holdback can apply to a specific portion of the work that reaches substantial performance or completion before the rest of the project, allowing that portion’s holdback to be assessed and potentially released on its own, separate timeline.

Can holdback be released before the whole project is finished?+

In some circumstances, yes. The Construction Act allows for annual or phased release of holdback on larger, longer-running projects, so an owner isn’t necessarily required to retain 10% of the entire multi-year contract price until the very end. These mechanisms have their own specific requirements and notice obligations.

What happens if an owner releases holdback too early?+

Releasing holdback before the applicable lien period has expired, or while a lien is still outstanding, can expose the owner to personal liability to unpaid subcontractors, suppliers, or workers up to the amount that should have been held back. This is one of the more common and costly mistakes owners make on construction projects.

Does holdback apply to residential renovation projects?+

Generally, yes — the Construction Act’s holdback requirement applies to improvements to real property broadly, which includes most residential renovation and construction work, not just large commercial projects. The percentage (10%) and general mechanics are the same regardless of project size, though the practical stakes are obviously smaller on a modest renovation.

Is holdback the same thing as a deposit?+

No. A deposit is money an owner typically pays upfront, before work begins, as a show of commitment or to cover initial costs. Holdback is money retained from payments otherwise owed to the contractor as the work proceeds, specifically to preserve funds that lien claimants may be entitled to reach.

Who is responsible for calculating and retaining holdback?+

The payer at each level of the contract — generally the owner paying the contractor, and in turn the contractor paying subcontractors — is responsible for retaining the required 10% holdback from its own payments. Holdback obligations exist at multiple levels of the contract chain, not just between the owner and the general contractor.

Can a lender or mortgage holdback be the same as the Construction Act holdback?+

Not necessarily. A construction lender may impose its own separate holdback or progress-draw conditions as part of financing the project, which is a contractual or lending requirement rather than the statutory holdback under the Construction Act. Projects can have both, and they serve different purposes even though the terminology overlaps.

What happens to holdback if a lien is registered against the property?+

If a lien is registered, the holdback generally needs to remain available to satisfy that claim (or claims) rather than being released to the contractor as usual. How the holdback is ultimately distributed often depends on how the lien claim is resolved, whether through payment, settlement, or a court decision.

Understand your agreement. Know your next step.

Ontario-wide, plain-English contract law information — built to help you make sense of your situation before you decide what to do next.

Free Consultation

Speak with a contract lawyer, free of charge

Tell us briefly what’s going on and we’ll be in touch to set up a free consultation about your contract situation.