Construction Liens in Ontario: How They Work and Filing Deadlines

What a construction lien secures, who can claim one, Ontario’s 60-day preservation and 90-day perfection deadlines, and what registering a lien does to title.

FreeConsultation Available
BA, JDSite Managed by Ryan Manilla
15+ yrsAt Ontario Bar
Published February 2, 2027Updated February 2, 2027Legally reviewed by Ryan J. Manilla, BA, JD

Key Takeaways

  • A construction lien lets a contractor, subcontractor, supplier, or worker secure a claim for unpaid work or materials against the title of the property they worked on.
  • A lien must generally be preserved within 60 days of the relevant triggering event, such as last supply of services or materials, or publication of a certificate of substantial performance.
  • Preserving a lien isn’t the end of the process — it must then be perfected within a further 90 days by issuing a court claim and registering a certificate of action.
  • Missing either deadline generally extinguishes the lien, though the underlying debt and any contract claim may still be pursued separately.
  • Registering a lien places a notice on the property’s title (encumbering it), which can complicate a sale, refinancing, or mortgage advance until the lien is resolved.
  • Lien rights exist alongside, not instead of, holdback obligations — the holdback an owner retains is generally the fund a lien claim is meant to reach.

What a construction lien actually secures

A construction lien is one of the defining features of Ontario’s Construction Act, 2019 (which replaced the former Construction Lien Act). It gives anyone who supplies services or materials to an improvement on real property a way to secure payment by registering a claim directly against the property’s title, rather than relying solely on a lawsuit against whoever owes them money.

The idea behind the lien is fairly simple: construction work increases the value of a property, and the people who contributed labour or materials to that increase in value should have a way to reach that value if they aren’t paid. A lien doesn’t create new money out of nowhere — it secures a claim against funds the owner is generally required to hold back during the project, and against the property itself, up to the value of the unpaid work or materials supplied.

It’s worth being clear about what a lien is not. It isn’t a judgment, and it doesn’t by itself determine that money is actually owed — it’s a notice and a security mechanism that preserves a claim while the underlying dispute about who owes what to whom still needs to be resolved, whether through settlement, court, or another process. A property owner who disputes a lien claim is generally entitled to defend it on the merits, the same as any other claim.

Who can claim a construction lien

Lien rights under the Construction Act extend to every level of the typical construction contract chain. General contractors who contracted directly with the owner can claim a lien for unpaid amounts owing to them. Subcontractors and sub-subcontractors, who may never have dealt with the owner directly, can also claim liens for the value of services or materials they supplied. Material suppliers who delivered goods to the project site can claim a lien, as can individual workers owed wages for labour performed on the improvement.

This layered structure is deliberate. Because an owner’s payment to a general contractor doesn’t guarantee that money flows down to the subcontractors and suppliers who actually did the work, the lien right gives everyone in the chain independent leverage to secure payment directly against the property, rather than depending entirely on the party above them passing payment along. Our article on subcontractor agreements in Ontario looks at how this plays out in the contract terms themselves.

A lien claim is generally limited to the actual value of what the claimant supplied and wasn’t paid for — it doesn’t allow a claimant to recover damages for other kinds of losses, such as lost profit on other jobs, through the lien process itself. Those kinds of claims, if they exist at all, are typically pursued separately as an ordinary breach of contract claim rather than through a registered lien.

The 60-day preservation deadline

The first and most important deadline is preservation. A lien claimant generally must register a claim for lien against the property’s title within 60 days of the relevant triggering event. What counts as the triggering event depends on the circumstances — commonly, it’s the last day on which the claimant supplied services or materials to the improvement, or the date a certificate of substantial performance for the relevant contract is published, whichever applies to the claimant’s situation.

Sixty days is not a long window in the context of a construction project, and it runs regardless of whether the parties are still negotiating, still exchanging invoices, or still hoping the payment dispute resolves informally. Missing this deadline generally extinguishes the lien right permanently — there’s typically no way to revive a lien once the preservation period has passed.

Worth knowing

Because the 60-day clock can start from different events depending on your role and the project’s timeline, identifying the correct triggering date is one of the most important — and most commonly disputed — questions in any lien claim.

It’s also worth noting that the Construction Act sets an overall maximum period after which lien rights generally expire even if an earlier triggering event hasn’t yet been pinned down, so claimants shouldn’t assume they can wait indefinitely for a clearer triggering date to emerge before acting. When in doubt about which date applies, treating the earliest plausible date as the deadline is the more cautious approach.

The 90-day perfection deadline

Preserving a lien is only the first step. To keep the lien alive, the claimant generally must then perfect it within a further 90 days after the lien was preserved. Perfection involves issuing a statement of claim in court setting out the basis for the lien claim, and registering a certificate of action against the property’s title referencing that court proceeding.

Perfection effectively converts the registered notice into an active court claim. Without it, a preserved lien generally expires at the end of the 90-day period, even if it was properly preserved in the first place. This two-step structure — preserve, then perfect — is one of the most unforgiving aspects of lien law, since each deadline runs independently and missing either one typically has the same result: the lien right is lost.

Because perfection requires formally starting a court proceeding, it’s a more involved and more costly step than preservation, and it generally brings the dispute into the ordinary litigation process from that point on. Some claimants preserve a lien promptly to protect their position, then use the 90-day window to try to negotiate a resolution before committing to the cost of actually perfecting it.

What registering a lien actually does

Registering a claim for lien places a notice directly on the property’s title at the relevant land registry office. This doesn’t transfer ownership or give the lien claimant any right to occupy or use the property — what it does is encumber the title, meaning the lien shows up in a title search and generally has to be dealt with before the property can be sold or refinanced cleanly.

In practice, this gives lien claimants real leverage even before a court proceeding is resolved, because most owners and lenders want a clear title and will move to resolve a registered lien — through payment, negotiation, or a formal discharge process — rather than leave it outstanding indefinitely. Our article on discharging a construction lien covers how an owner can remove a lien from title, including by posting security in its place.

What happens after a lien is registered

Once a lien is preserved and perfected, it generally proceeds like other court litigation, moving through pleadings, evidence, and potentially a trial if it isn’t resolved earlier. In practice, many lien claims settle well before trial, since the pressure a registered lien places on a property’s title often brings the parties to the table faster than an ordinary breach of contract claim would.

Liens also interact closely with other parts of the Construction Act — the holdback an owner is required to retain is generally the fund a lien claim is intended to reach, and a construction bond may sometimes stand in as alternative security. For disputes that don’t fit neatly into a lien claim, Ontario’s interim adjudication process offers another, faster route to a binding (if interim) resolution. This article explains generally how liens work in Ontario; it isn’t a substitute for confirming the specific deadlines that apply to a particular project, which can turn on facts a general summary can’t capture. See the construction insights hub for more, or our contact page if you have a general question about this site.

Legally reviewed by Ryan J. Manilla, BA, JDGeneral legal information, not personalized legal advice.Read our review policy →

More in Construction

Continue reading

Construction

Construction Contracts in Ontario: Key Terms to Know

Walks through what a solid construction contract should cover — scope, price and payment schedule, change orders, holdback, substantial performance, warranty and dispute resolution — and how CCDC standard forms fit in.

February 1, 2027
Construction

Holdback Requirements Under Ontario’s Construction Act

Covers the mandatory 10% holdback, why it exists, basic versus finishing holdback, when it becomes releasable, and annual or phased release on longer projects.

February 3, 2027
Construction

Prompt Payment Rules in Ontario Construction Contracts

Covers the proper invoice requirement, the cascading 28-day and 7-day payment timelines, notices of non-payment, and how the regime is meant to keep money flowing down the payment chain.

February 4, 2027
Construction

Interim Adjudication for Ontario Construction Disputes

Explains the fast interim adjudication process under the Construction Act — which disputes qualify, how notice and appointment work, the 30-day decision timeline, and how it differs from mediation, arbitration and litigation.

February 5, 2027
Construction

Home Renovation Contracts in Ontario: What to Include

Key terms every homeowner-renovator contract should cover — scope, pricing, milestone-based payment, permits, change orders, cleanup and warranty — plus red flags to watch for.

February 6, 2027
Construction

Subcontractor Agreements in Ontario

What a general contractor–subcontractor agreement should cover, including pay-when-paid versus pay-if-paid clauses, prompt payment, insurance and indemnities, and the lien rights subcontractors keep regardless of contract wording.

February 7, 2027
Construction

Construction Deficiency Claims in Ontario

How to tell a deficiency from normal wear, document it properly, use holdback as leverage, and the options available when a contractor won’t fix defective work.

February 8, 2027
Construction

Substantial Performance in Ontario Construction Projects

What substantial performance means under the Construction Act, how it’s determined, and why publishing a certificate starts lien deadlines and can trigger holdback release.

February 9, 2027
Construction

Change Orders in Ontario Construction Contracts

Explains why scope changes need a written change order rather than a verbal instruction, covering price, schedule and holdback impacts, the typical approval process, and the risks unrecorded extras create for owners and contractors alike.

February 10, 2027
Construction

Performance and Labour & Material Bonds in Ontario

Breaks down what a performance bond protects versus a labour and material payment bond, when bonding is typically required, and how a bond claim against the surety generally proceeds.

February 11, 2027
Construction

Discharging or Vacating a Construction Lien in Ontario

Walks through an owner’s options when facing a registered lien — paying it out, negotiating a holdback-based arrangement, or posting security to vacate the lien from title — plus what happens when a claimant misses the Construction Act’s deadlines.

February 12, 2027
Construction

Homeowner vs. Contractor Disputes in Ontario

Covers common flashpoints such as incomplete work, overruns, delays and quality, practical first steps, holdback and lien dynamics from the homeowner’s side, and escalation through Small Claims or Superior Court.

February 13, 2027

FAQ

Frequently asked questions

What is a construction lien in Ontario?+

A construction lien is a legal claim registered against the title of a property, available to contractors, subcontractors, suppliers, and workers who supplied services or materials to a project and weren’t paid in full. It’s a security mechanism created by Ontario’s Construction Act, letting unpaid parties stake a claim against the property itself rather than relying only on a lawsuit against the person who owes them money.

Who can register a construction lien in Ontario?+

Anyone who supplied services or materials to an improvement — general contractors, subcontractors, sub-subcontractors, material suppliers, and individual workers — can generally claim a lien for the unpaid portion of what they’re owed. The right exists at every level of the contract chain, not just for the party contracted directly with the owner.

How long do I have to preserve a construction lien in Ontario?+

A lien must generally be preserved within 60 days of the relevant triggering event, which depends on your role and the circumstances — commonly the last day services or materials were supplied, or the date a certificate of substantial performance is published. Missing this deadline generally extinguishes the lien right permanently.

What does it mean to “preserve” a lien versus “perfect” it?+

Preserving a lien means registering a claim for lien against the property’s title within the 60-day deadline. Perfecting the lien is the next step — issuing a statement of claim in court and registering a certificate of action against the title — which generally must happen within 90 days after the lien was preserved. Both steps are required; preserving a lien without later perfecting it generally causes it to expire.

What happens if I miss the lien deadline?+

Missing the 60-day preservation deadline, or the subsequent 90-day perfection deadline, generally extinguishes the lien right permanently — it typically cannot be revived afterward. The underlying debt doesn’t necessarily disappear, since a breach of contract or debt claim may still be available, but the valuable security a lien provides against the property itself is lost.

Does registering a lien stop a property from being sold?+

Not automatically, but it can make a sale or refinancing considerably harder, because a registered lien is an encumbrance on title that most buyers and lenders won’t accept without it being addressed first. In practice, many sales proceed only after the lien is paid out, discharged, or otherwise resolved.

Can a homeowner remove a construction lien from their property?+

Yes, through several possible routes, including paying out the claim, negotiating a resolution, or applying to have the lien discharged from title (sometimes by posting security in its place). This process is covered in more detail in our article on discharging a construction lien.

How much can be claimed through a construction lien?+

A lien claim is generally limited to the value of the services or materials actually supplied and unpaid, and it’s further limited by the amount of holdback and any other funds the owner is required to retain under the Construction Act. It isn’t a mechanism for claiming damages beyond the unpaid contract amount.

Do I need a lawyer to register a construction lien?+

It isn’t strictly required, but the preservation and perfection process involves strict statutory deadlines and specific registration requirements, and getting a step wrong can cost you the lien right entirely. Many lien claimants, particularly for larger amounts, choose to get legal assistance given how unforgiving the deadlines are.

What’s the difference between a construction lien and a mortgage?+

Both are registered against a property’s title, but they arise differently — a mortgage is a voluntary security interest granted by the owner to a lender, while a lien arises automatically by statute in favour of someone who supplied services or materials, once statutory conditions are met. Priority between a lien and a mortgage can depend on timing and the specific facts involved.

Can a subcontractor lien a property if the general contractor was paid?+

Yes. A subcontractor’s lien right arises from supplying services or materials to the project, not from whether the general contractor above them was paid. This is part of why holdback exists — to make sure funds remain available further down the contract chain even where the owner has already paid the general contractor.

Does a certificate of substantial performance affect lien deadlines?+

Yes, significantly. Publishing a certificate of substantial performance starts the 60-day preservation clock for liens related to the contract covered by that certificate, which is one reason the timing and publication of that certificate matters so much under the Construction Act. See our article on the certificate of substantial performance for more detail.

Understand your agreement. Know your next step.

Ontario-wide, plain-English contract law information — built to help you make sense of your situation before you decide what to do next.

Free Consultation

Speak with a contract lawyer, free of charge

Tell us briefly what’s going on and we’ll be in touch to set up a free consultation about your contract situation.